Offshore Structural Analysis: Global vs Local Analysis, and When FEA Is Needed

Figure 1: From global model to local check

Offshore Structural Analysis: Global vs Local Analysis, and When FEA Is Needed

In short: global analysis tells you how loads travel through the whole structure. Local analysis checks the places where those loads concentrate. Finite element analysis (FEA) can support both global and local structural analysis, particularly where geometry, structural behaviour or load paths require detailed numerical assessment. Getting the split right keeps the analysis proportionate to the question being asked.

What global structural analysis does

A global analysis models the complete structure, or the complete load-bearing system of interest, using beam, shell or combined elements as appropriate to the structure. Its purpose is to find:

  • how loads are shared between members and supports
  • the resulting member forces and moments
  • support reactions and load paths into foundations, decks or vessel structure
  • overall deflections and stiffness

The model is run for the load cases defined in the design basis. For offshore structures and equipment these typically include self-weight, equipment and operational loads, environmental loads such as wind, wave and current where relevant, and temporary-phase loads such as transport accelerations or lifting loads. They are then combined as the applicable design code or client specification requires.

For fixed steel offshore structures, ISO 19902 and API RP 2A are widely used design references. Many projects also apply company or client specifications on top of them.

The output is a set of member and joint utilisations, together with the forces at the boundaries of any region that needs closer checking.

What local analysis does

Local analysis zooms in on a region where the global model is too coarse to give a reliable answer, for example:

  • connections and joints between members
  • stiffened plates and deck panels under concentrated loads
  • openings and cut-outs in plated structures
  • lifting points, padeyes and their connection into the main structure
  • equipment supports and load-spreading details

Local checks may include loads and boundary conditions derived from global analysis, together with directly applied local loads where relevant. That link matters: a local model is only as good as the boundary forces and/or displacements and the support conditions it receives.

Figure 1: From global model to local check
Figure 1: From global model to local check. A global structural model (beam, shell or combined) feeds the local check, which uses either code formulas or an FE model with appropriate boundary forces and/or displacements. If local reinforcement changes the load path, the global model is updated.

When is finite element analysis needed?

Many members and standard joints can be checked with the formulas in the applicable design code. FEA earns its place when:

  • the geometry is irregular: plated structures, cut-outs, brackets or non-standard connections where no code formula applies directly
  • stresses concentrate: around openings, at load introduction points, or at hot spots relevant to fatigue
  • load spreading is unclear: for example how a concentrated equipment load spreads through deck plate, stiffeners and girders
  • plated buckling governs: panels and webs under combined in-plane loads
  • hand calculations become too conservative: a refined analysis can show adequate capacity and avoid unnecessary reinforcement

Fatigue is a common reason for local modelling. Guidance such as DNV-RP-C203 describes how structural hot-spot stresses are derived from shell or solid models at welded details and assessed against the appropriate S-N curves.

If a code check gives a clear answer with reasonable margin, a full FE model may add cost without adding confidence. The choice of method belongs in the agreed scope.

Points that make an FE model reliable

  • Element choice: beam elements for frames; shell elements for plates and stiffened panels; solid elements where three-dimensional stress behaviour, complex geometry, contact or through-thickness effects require detailed representation.
  • Mesh: refined where stresses concentrate, with a sensitivity check where results depend on mesh size.
  • Boundary conditions: representative of how the region is actually supported, and consistent with the global model.
  • Load application: loads introduced as they act in reality (distributed over footprints, not as artificial point loads that create false peaks).
  • Verification: reaction totals checked against applied loads, deformed shapes reviewed for plausibility, and key results compared with a simple hand calculation.
Figure 2: Evaluating FE stresses – a structural hot-spot stress example
Figure 2: Evaluating FE stresses, shown with a structural hot-spot stress example for fatigue at a weld toe. Surface stresses at defined read-out points are extrapolated to the weld toe. The right stress evaluation method depends on the failure mechanism and the applicable design criteria.

Practical challenges on real offshore jobs

The theory is straightforward. Most of the difficulty comes from the conditions on an actual job:

  • The drawings do not match the structure. On brownfield work, drawings are often incomplete or out of date. Earlier modifications may be undocumented, and corrosion may have reduced plate and member thickness. A short site survey and thickness measurements at critical locations are usually cheaper than designing around unknowns with blanket conservatism.
  • The load data is preliminary. Vendor weights and centres of gravity often change during design. Applying a weight contingency and checking a centre-of-gravity envelope, rather than a single point, avoids repeating the analysis when the final data arrives.
  • Temporary phases govern. Lifting, loadout and sea transport can load supports, padeyes and local structure more heavily than the in-place condition. Lifting assessments should account for applicable dynamic effects and load distribution factors, including skew factors where relevant. Transport assessments need the vessel accelerations. These cases belong in the design basis from the start, not after the in-place design is finished. Our Transportation & Installation Engineering service covers these phases.
  • FE peaks are taken at face value. Numerical stress singularities may occur at idealised sharp corners, point supports and weld details, resulting in mesh-dependent peak stresses. These peaks cannot simply be used as design stresses, and they cannot be disregarded either. They must be evaluated by the method appropriate to the failure mechanism and the applicable design criteria: for example, a structural hot-spot stress for weld-toe fatigue (Figure 2), or the code-defined approach for yielding, buckling or fracture. Misreading them leads either to unnecessary reinforcement or to an unconservative result.
  • The local model is cut too close. If sub-model boundaries sit right next to the area of interest, the boundary assumptions drive the answer. Boundaries should be placed far enough away that the result does not depend on them.
  • Offshore hot work is expensive. Welding offshore needs permits, habitat or shutdown planning and offshore manpower. A refined local analysis that shows existing capacity, or that limits reinforcement to bolted or clamped solutions, can save far more than the cost of the analysis.

Inputs needed to start

  • drawings or a model of the structure (as-built where it already exists)
  • loads to be assessed: weights, centres of gravity, operational, environmental or temporary-phase loads
  • the applicable design code or client specification
  • material grades
  • the required deliverables and any review requirements

Agreeing these before the main analysis starts avoids rework when assumptions change. In our Structural Analysis & Design service, inputs, assumptions, interfaces and exclusions are agreed before the main work starts.

A hypothetical example

Hypothetical example, for illustration only: a new equipment skid is to be installed on an existing offshore deck. A global check confirms that the deck girders and supporting structure can carry the added load and any temporary installation loads. A local FE model of the deck plate and stiffeners under the skid feet then checks how the concentrated loads spread, whether the plate and stiffeners have sufficient capacity, and whether local reinforcement or load-spreading plates are needed. The results are documented in a calculation report, with fabrication drawings for any reinforcement.

Figure 3: Load path from an equipment skid into an existing deck (hypothetical)
Figure 3: Load path from a new equipment skid into an existing deck: skid feet, deck plating, stiffeners, primary girders, then the supporting structure. The connections and welds at each transfer point are marked for local verification. Hypothetical example for illustration only.

Where reinforcement is needed, the fabrication drawings can be produced alongside the calculations; see our Offshore Drafting & Design Support service.

Summary

Global analysisLocal analysis / FEA
Question answeredHow loads travel through the structureWhether a specific region can carry them
Typical modelGlobal structural model (beam, shell or combined)Detailed shell or solid model of one region
Main outputsMember forces, reactions, deflections, utilisationsStresses, local capacity, reinforcement need
Depends onDesign basis and load casesBoundary forces and/or displacements from the global analysis

Frequently asked questions

Is FEA always more accurate than hand calculations?

No. FEA is only as good as its geometry, boundary conditions, loads and result interpretation. For standard members and joints covered by code formulas, a hand or spreadsheet check is often just as reliable and easier to review.

Can an existing deck take new equipment without reinforcement?

Sometimes. A global check of the girders and supports, followed by a local check of the plate and stiffeners under the equipment feet, shows whether capacity is sufficient. A refined analysis often avoids reinforcement that a conservative first check would require.

What should be agreed before the analysis starts?

The design basis: geometry, loads, load cases, the applicable code or client specification, material grades, and the deliverables. Agreeing these up front prevents rework.

Need structural analysis for an offshore structure, deck or equipment foundation? Poseidon Offshore Energy provides global and local structural analysis, FEA, strength and fatigue checks, and design verification, with calculation reports and fabrication drawings. Send us your drawings, loads and schedule, and our Engineering Team will come back with a defined scope.